AMERICAN SpiralWeld Pipe Performs in New Music City Stadium Project

Crews with Garney Construction had to coordinate the installation of the new sewer force main while numerous events were held at Nissan Stadium, including the Indy Music City Grand Prix, Taylor Swift Eras Tours, Tennessee Titans and Tennessee State University football games.

What do the Indy Music City Grand Prix, Taylor Swift Eras Tours concerts, Country Music Awards Festival, and college and NFL football games have in common? These and other events were held at Nissan Stadium in Nashville, Tennessee, in the spring, summer and fall of 2023. At the same time, crews from Garney Construction were installing approximately 2,200 feet of 60-inch AMERICAN SpiralWeld Pipe. The pipe needed to be installed before groundbreaking could begin on the New Nissan Stadium in early- to mid-2024. The new sports and entertainment venue is expected to open in 2027.

Approximately 2,200 feet of 60-inch AMERICAN Steel Pipe was installed near Nissan Stadium in Nashville, Tennessee.

This project involved relocating an existing sewer force main near the site of the new stadium, which will be located adjacent to the current Nissan Stadium. Pipe shipments were temporarily sidelined throughout the six-month project to accommodate fans and guests alike. Project work began in late April 2023 and was completed at the end of November 2023.

“The advantage of using spiral-welded steel pipe for this project was its versatility,” said AMERICAN Sales Engineer Jim Williamson. “This was not a conventionally designed project, and the owner and contractor had a quick turnaround time to complete the work in preparation for the groundbreaking.”

Another challenge was minimal space to store the 60-inch spiral-welded steel pipe in the parking lot of Nissan Stadium. “The pipe staging area was very confined, about 520 feet by 20 feet,” said Garney Project Manager Tony Naredo. “With help from AMERICAN, we were able to get pipe on-site when we needed it and still work around whatever events were happening at Nissan Stadium. AMERICAN was very helpful and responsive throughout the project.”

“The advantage of using spiral-welded steel pipe for this project was its versatility,” said AMERICAN Sales Engineer Jim Williamson. “This was not a conventionally designed project, and the owner and contractor had a quick turnaround time to complete the work in preparation for the groundbreaking.”

The spiral-welded steel pipe was manufactured in Columbia, South Carolina. AMERICAN SpiralWeld Pipe has two other manufacturing facilities in Flint, Michigan, and Paris, Texas.